Peak pipeline construction is currently underway. The field workforce exceeded 4,000 as CGL added 528 workers in the field. Grading is now underway in six of the eight sections. There was also 2,500 piles installed at the Wilde Lake Compressor Station.
In terms of total numbers construction progress still sits under 20 per cent at 18.8 and the overall progress is sitting at 34.6 per cent. As mentioned before the exact number of workers on this project currently is 4,016.
Coastal GasLink provided a full section by section breakdown of the progress on their website.